The first one of two turbines which landed in Prince Rupert on Dec. 2, is headed to Site C Dam in Fort St. John on Jan 10. The extraordinary wide load created traffic advisories and road closures along highway 16 during the week of Jan. to 14. (Photo: supplied by Tasha McKenzie)

The first one of two turbines which landed in Prince Rupert on Dec. 2, is headed to Site C Dam in Fort St. John on Jan 10. The extraordinary wide load created traffic advisories and road closures along highway 16 during the week of Jan. to 14. (Photo: supplied by Tasha McKenzie)

VIDEO: Second massive turbine passes through Telkwa en route to Site C Dam

The load is 221-feet-long, 26-feet wide and weighs more than 170 tonnes

The second of two massive hydroelectric turbines headed for the Site C Dam in Fort St. John passed through Telkwa in around 2:45 Jan 29.

The first of three shipments each of two 170-tonne turbine runners measuring 26 ft (8 metres) wide by 17 feet (5 metres) tall was originally spotted by Black Press Media on Dec. 2 being unloaded by crane from a vessel in the inner harbour onto a barge for transportation to shore.

Video by Airika Owen

The extraordinarily wide, 221-ft long load is travelling by night to be as minimally disruptive to traffic as possible. Today, it is resting at Hungry Hill between Telkwa and Houston.

READ MORE: Massive turbines for Site C unloaded in Prince Rupert

“The turbine runners are the heaviest unassembled single project component of equipment related to the generating station,” Dave Conway, community relations manager for the Site C project told Black Press Media.

The specially built cargo was constructed and shipped from Sao Paulo, Brazil as part of a $470 million contract between BC Hydro and Voith Hydro Canada. The hydroelectric turbines are unique, built to suit the needs of the Site C Dam requirements.

The transportation firm Omega Morgan, which specializes in oversized load transportation is overseeing the movement between Prince Rupert and the Site C Dam.

The turbines are set to be installed at Site C in 2022. There will be six vertical axis turbines in total, with two more shipments to be confirmed, however, not expected until the spring of 2021 and the summer of 2022, Conway said.

With files from Thom Barker

READ MORE: Work begins on Site C generators (with video)



editor@interior-news.com

Like us on Facebook and follow us on Twitter

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

(Phil McLachlan/Capital News)
Murder charge laid in February 2020 stabbing death of Smithers man

Michael Egenolf is charged with the second-degree murder of Brodie Cumiskey

Island Health chief medical officer Dr. Richard Stanwick receives a first dose of Pfizer vaccine, Dec. 22, 2020. (B.C. government)
COVID-19: B.C. seniors aged 90+ can start to sign up for vaccination on March 8

Long-term care residents protected by shots already given

A health care worker prepares to test a Coastal GasLink field worker for COVID-19. (Coastal GasLink photo)
Coastal GasLink begins COVID screening of pipeline workers

Construction is once again ramping up following Northern Health approval of COVID management plan

FILE – A COVID-19 vaccine being prepared. (Olivia Sullivan/Sound Publishing)
B.C. seniors 80 years and older to get COVID vaccine details over next 2 weeks: Henry

Province is expanding vaccine workforce as officials ramp up age-based rollout

Design work continues for planned new hospital

Construction contract still in the works

Beginning late Tuesday, anti-pipeline protesters blocked the intersection of Hastings Street and Clark Drive in Vancouver. (Instagram/Braidedwarriors)
Demonstrators block key access to Vancouver port over jail for pipeline protester

They group is protesting a 90-day jail sentence handed to a fellow anti-pipeline protester

A discarded blue surgical mask is shown hanging in a bush in Montreal, Sunday, Dec. 6, 2020, as the COVID-19 pandemic continues in Canada and around the world. THE CANADIAN PRESS/Graham Hughes
B.C. RMT suspended for not wearing a mask after confirmed by undercover clients

College of Massage Therapists has 5 open files, said suspension necessary to protect public

A boat caught fire in Ladysmith Harbour on Saturday morning. (Photo submitted)
Missing woman’s remains recovered after Vancouver Island boat fire

Remains of a 60-year-old woman recovered after Feb. 27 boat fire took her life

This poster, spreading misinformation regarding COVID-19 restrictions, has been popping up in communities across Vancouver Island.
Poster popping up on Vancouver Island falsely claims COVID restrictions are over

Unattributed poster claims COVID restrictions ended March 1; Island Health responds

COVID-19 vaccines were available at a site on East Pender in Vancouver’s Downtown Eastside Feb. 25. (Twitter/Sarahblyth17)
Vancouver’s Downtown Eastside residents offered $5 after getting COVID-19 vaccine

It’s an effort to ‘incentivize people to engage,’ says B.C. Health Minister Adrian Dix

</p>
A survey by Statistics Canada finds Black Canadians earn less than non-visible minority Canadians despite having higher levels of education. (The Canadian Press file photo)
COVID-19 worsened unemployment picture for Black Canadians

Black Canadians also more likely to suffer other hardships

Most Read