Ottawa reports $29M profit at Trans Mountain but critic says accounting flawed

The report, based on numbers from Canada Development Investment Corp., notes operating expenses of $366 million

A report that says the Trans Mountain pipeline system has earned net income of $29 million in the 19 months since it was purchased by Ottawa relies on faulty accounting, according to a vocal critic of the project.

The oil conduit running from Edmonton to the Vancouver area had operating revenues of $728 million, mainly from user tolls, since it was purchased in the fall of 2018 from Kinder Morgan Canada for about $4.4 billion, according to an online analysis from the Office of the Parliamentary Budget Officer posted Wednesday.

The report, based on numbers from Canada Development Investment Corp. — which owns the pipeline on the government’s behalf — notes operating expenses of $366 million, financing costs of $223 million and a $172-million depletion and depreciation expense on the pipeline assets.

Those were offset in part by a $61-million tax recovery thanks to a decrease in Alberta’s corporate tax rate as well as lower income taxes for the period ended March 31.

“An increase in construction costs or changes in the price of oil could affect profitability but for the first months up to March 2020, the pipeline seems to have been profitable,” said Parliamentary Budget Officer Yves Giroux in an interview.

In a report last November, the Cleveland-based Institute for Energy Economics and Financial Analysis charged that Trans Mountain is receiving hundreds of millions of dollars in hidden direct and indirect federal and provincial government subsidies.

It listed the Alberta tax cut as a subsidy even though it applies to all businesses and said the project also benefits from lower-than-market interest rates given its high level of risk.

The Department of Finance, however, responded at the time that the government does not consider any part of its investment in the pipeline to be a subsidy.

“This (report) is a very narrow focus and does not include the massive subsidies that have been offered to the project, direct and indirect subsidies,” said IEEFA financial analyst Kathy Hipple on Wednesday.

In February, Trans Mountain announced a revised construction cost estimate for its expansion project, bumping it up by about 70 per cent from $7.4 billion to $12.6 billion.

In spite of the increased cost and the dramatic downturn in oil prices this year due to the pandemic fuelled economic downturn, the pipeline has not written down its goodwill, although oil producers have recognized billions in such writedowns, Hipple said.

“This is astonishing to me,” she said.

But Giroux defended the numbers, noting that pipeline economics are different than oil production economics.

“The issue of oil prices could affect future revenue but the tolls are being determined by the Canadian Energy Regulator so tolls are not as dependent on the price of oil itself,” he said.

“They’re dependent on the volume, so as long as Trans Mountain has secured contracts to fill the majority of its expanded capacity, revenues should not be too much at risk.”

The PBO added the CDIC has revised the sensitivity analysis it uses to determine goodwill impairments.

It previously provided estimates for the impact of a 10 per cent increase in construction costs or a one-year delay in construction, along with higher interest rates.

It now estimates a 0.25 per cent increase in interest would have a $500 million impact on the value of the project, a $600 million increase in construction costs would have a $200 million impact and the impact of a one-year delay plus a $600-million cost increase would be $900 million.

Dan Healing, The Canadian Press

Like us on Facebook and follow us on Twitter.

Want to support local journalism? Make a donation here.

Pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Brucejack mine fatality identified

Patrick Critch was from Newfoundland

Here are Kitimat’s 10 worst streets and intersections for collisions

A look at the top 10 roads and intersections for crash numbers in Kitimat.

Pretivm Resources reports fatality at Brucejack mine

The isolated incident occurred last Friday, and the employee passed away on Sunday in hospital

QUIZ: How much do you know about British Columbia?

On this B.C. Day long weekend, put your knowledge of our province to the test

“How many more years is this going to continue?”: Kitimat resident wants better District response to front yard sinkholes

The sinkholes are caused by an aging storm sewer, which the District says they are working to fix.

Airlines dispute Dr. Henry’s claim they ‘very rarely’ give accurate COVID contact tracing info

Air Canada, WestJet say they provide names and contact information

‘We all have anxieties’: B.C.’s top doctor addresses return-to-school fears amid COVID-19

Dr. Bonnie Henry promises school restart plan safe for B.C. kids

B.C. fish harvesters receive long-awaited details on pandemic benefits

Applications to the $470-million federal assistance programs will open Aug. 24

Abbotsford mom worried about her two kids in Beirut following explosion

Shelley Beyak’s children were abducted by their dad in 2018

Young Canadians, hospitality workers bear the brunt of mental strain in 2020: report

A study by Morneau Shepell points to economic uncertainty in the pandemic as the cause for angst

Health Canada recalling more than 50 hand sanitizers in evolving list

Organization says to stop using products listed, and to consult a health-care professional

Airborne hot dog strikes Greater Victoria pedestrian

Police called to 4200-block of Quadra Street for hot dog incident

B.C. scientist, 63, protests in trees set to be removed for Trans Mountain pipeline

Tim Takaro is reaching new heights as he tries to stall the pipeline expansion project in New Westminster

Dwindling B.C. bamboo supply leaves Calgary Zoo biologists worried about pandas

Zoo has been trying to send pandas back to China since May

Most Read