LNG Canada project gradually taking shape

Extensive worker camp now being assembled

Born in Ireland but having spent years overseeing liquefied natural gas (LNG) construction projects in Australia, LNG Canada’s just-arrived general manager for its $40 billion facility in Kitimat is firm about his expectations.

“We want this to be the safest project on earth,” Vince Kenny says of construction which has just passed the one year mark leading to a planned finish in 2024.

With just under 1,000 people now working at the 400-hectare site, now is the time to cement that standard, he says.

“By the time we get to 5,000 people, we will have that culture in place,” Kenny said of this project which will be his seventh. “Unless you’ve got a culture, all the systems, processes and procedures are ineffective.”

Employees begin each shift reviewing the work plan, a procedure called a toolbox discussion.

“We’re here to take care of one another,” says Kenny, translating the IIF acronym that’s the hallmark of LNG Canada — Incident and Injury Free.

Even a brief tour of the works by a group of journalists from across B.C. starts with a video of LNG Canada workers outlining safety and security, the two words being almost interchangeable.

Workers have ID cards to be ‘badged in,’ creating an electronic record of their presence. They’re required to stay within their designated work area. There are constant security patrols. Vehicles are inspected for any fluid leaks before entry. There’s specific mention of drug-sniffing dogs too.

READ MORE: Okanagan company wins contract for LNG Canada project in Kitimat

No-one gets on the site without basic safety equipment — hardhat, safety glasses, a high visibility vest, work boots and gloves. The driver of the tour bus taking the journalists to the site points out emergency exit windows. He brandishes a small hammer to smash a window if necessary. The bus doesn’t move until each passenger clicks in their seatbelt.

Victor Kenny, LNG Canada general manager

With Kenny is Trevor Feduniak who arrived in Kitimat in mid-2016. As the project site manager, he was one of the first senior LNG Canada people on location, overseeing the clearing of the former Methanex site and then expanding its footprint.

Although the project was not given the formal go-ahead until last October by LNG Canada’s investors Shell, PETRONAS from Malaysia, PetroChina from China, Mitsubishi Corporation from Japan and Korean-owned KOGAS, crews had been fully occupied raising up the location to a construction standard and to safeguard it against the possibility of tsunami sweeping inland from the Douglas Channel.

The fill comes from the nearby Sandhill, a mountain of material Feduniak describes as perfect for its material composition. One million cubic metres has already been transferred, edging away at the overall 2.5 million cubic metres that will have to be moved and placed in preparation for the arrival of two massive processing modules. From there, the gas will be transported via a pipeline from northeastern B.C., super-cooled to a liquid state for storage and then shipped out on specialized tankers to Asian customers.

“This is what we call coming out of the ground,” Feduniak explains as a tour bus winds its way through the site, encountering massive material-carrying trucks along the way.

Two streams that cross the site, the Kitimat Side Channel and Beaver Creek, were diverted to ensure Fluor-JGC has dry and stable conditions on which to construct the plant.

“When you disturb one habitat, you have to compensate with two [enhancement measures],” says Feduniak of the environmental work that was involved.

He compares the detailed water course replacement work for fish and other habitat to that of a landscaped Japanese garden.

One corner of the project site contains what, to the untrained eye, looks like sections of pipe stacked metres above the ground.

What they are are the pilings, 40 metres long, that will be driven into the ground upon which the two processing buildings will sit.

READ MORE: LNG Canada cost to exceed stated $40 billion price tag

Those processing modules being built in Asia are to be 70 metres long, 35 metres wide and 50 metres tall, the approximate height of a 13-storey commercial building.

They’ll be shipped to Kitimat in modular segments and assembled on-site, being transported to their final resting place via an elaborate series of interconnected trailers with hundreds of wheels controlled by a single operator using a remote control. So sophisticated is the transport system that the operator is able to place the modules within centimetres of where they need to be located.

The sheer height of the modules has meant raising Rio Tinto BC Works’ power lines that cross the site to deliver power to the smelter from Kemano, so that the modules can fit comfortably underneath when being moved.

One of the more visible above-ground projects now underway is that of the worker camp, Cedar Valley Lodge, which is being built by the ATCO-Bird joint venture, for another joint venture between Fluor Corporation and JGC, the overall general contractor on the project.

There’ll be two living unit sections with a series of common buildings in the middle.

One of the modular accommodation sections is now being assembled with a finishing schedule of next spring to meet a first goal of 1,500 “heads in beds” with 1,000 more beds to be added each quarter thereafter to the final total of 4,500.

Unlike camps of past, each worker will have his or her own bathroom and each room will have its own TV. There’ll be sound dampening and other acoustic methods so that sleeping quarters will be as quiet as possible. The living areas will be co-ed.

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, an entertainment centre, a licensed lounge, a medical clinic, storage for luggage and housekeeping and maintenance facilities.

There’ll be landscaping around the area and informational material describes the facility as having the “largest core footprint” of its kind in Canada.

“You want your workers to come here and then want to come back,” said LNG Canada spokesperson Susannah Pierce of the atmosphere and amenities of the facility.

More than 4,500 people will be onsite at any one time at the peak of construction, requiring between 7,000 to 7,500 people in all given the shift work nature of the project. Workers will be onsite for 14 days at a time, returning after a seven-day break.

All this compares to another large worker camp in B.C. — the 1,600-room facility at B.C. Hydro’s Site C project in northeastern B.C.

With accommodation facilities now underway, there’s other activity on the waterfront at two terminal sites.

LNG Canada is building Rio Tinto a new wharf in exchange for taking over the aluminum smelting company’s existing wharf. Dredging is now going on as part of that project.

kitimatLNGlng canada

Get local stories you won't find anywhere else right to your inbox.
Sign up here

 

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada project site manager Trevor Feduniak arrived in Kitimat in mid-2016. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

LNG Canada’s ‘fish ladder’ at Anderson Creek, which allows fish to migrate despite construction-related work. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

The middle buildings will contain administration offices, sports and recreation facilities including male and female gyms, kitchen and dining facilities, and other features. (Natalia Balcerzak/Terrace Standard)

Just Posted

(Phil McLachlan/Capital News)
Murder charge laid in February 2020 stabbing death of Smithers man

Michael Egenolf is charged with the second-degree murder of Brodie Cumiskey

Island Health chief medical officer Dr. Richard Stanwick receives a first dose of Pfizer vaccine, Dec. 22, 2020. (B.C. government)
COVID-19: B.C. seniors aged 90+ can start to sign up for vaccination on March 8

Long-term care residents protected by shots already given

A health care worker prepares to test a Coastal GasLink field worker for COVID-19. (Coastal GasLink photo)
Coastal GasLink begins COVID screening of pipeline workers

Construction is once again ramping up following Northern Health approval of COVID management plan

FILE – A COVID-19 vaccine being prepared. (Olivia Sullivan/Sound Publishing)
B.C. seniors 80 years and older to get COVID vaccine details over next 2 weeks: Henry

Province is expanding vaccine workforce as officials ramp up age-based rollout

Design work continues for planned new hospital

Construction contract still in the works

Health Minister Adrian Dix looks on as Dr. Bonnie Henry pauses for a moment as she gives her daily media briefing regarding COVID-19 for British Columbia in Victoria, B.C. THE CANADIAN PRESS/Jonathan Hayward
7 additional deaths and 542 new COVID-19 cases in B.C.

Provincial health officials reported 18 new COVID-19 cases linked to variants of concern

The City of Vancouver estimates there are 3,500 Canada geese in the city right now, and that number is growing. (Bruce Hogarth)
Help tame Vancouver’s Canada goose population by reporting nests: park officials

The city is asking residents to be on the lookout so staff can remove nests or addle eggs

Chief Justice Christopher Hinkson (Office of the Chief Justice)
Judge questions whether B.C.’s top doctor appreciated right to religious freedom

Lawyer for province says Dr. Henry has outlined the reasons for her orders publicly

A sample of guns seized at the Pacific Highway border crossing from the U.S. into B.C. in 2014. Guns smuggled from the U.S. are used in criminal activity, often associated with drug gangs. (Canada Border Service Agency)
B.C. moves to seize vehicles transporting illegal firearms

Bill bans sale of imitation or BB guns to young people

BC Housing minister David Eby is concerned that Penticton council’s decision to close a local homeless shelter will result in a “tent city” similar to this one in Everett, Wa. (Olivia Vanni / Black Press file)
‘Disappointed and baffled’ B.C. housing minister warns of tent city in Penticton

Penticton council’s decision to close a local homeless shelter could create tent city, says David Eby

The first of Fisheries and Oceans Canada’s long-range maritime patrol aircraft—the Dash-8—becomes operational. (Photo supplied by PAL Aerospace)
Fisheries and Oceans Canada’s new De Havilland Dash-8-100 long-range surveillance air craft is capable of staying aloft for eight to 10 hours for a variety of missions up and down the B.C. coast. (Photo supplied by PAL Aerospace)
New plane will double DFO’s surveillance capacity in B.C.

The Dash-8 will fly out of Campbell River for enforcement, conservation missions

A recently published study out of UBC has found a link between life satisfaction levels and overall health. (Pixabay)
Satisfied with life? It’s likely you’re healthier for it: UBC study

UBC psychologists have found those more satisfied with their life have a 26% reduced risk of dying

A vial of some of the first 500,000 of the two million AstraZeneca COVID-19 vaccine doses that Canada has secured through a deal with the Serum Institute of India in partnership with Verity Pharma at a facility in Milton, Ont., on Wednesday, March 3, 2021. THE CANADIAN PRESS/Carlos Osorio - POOL
Federal panel recommends 4-month gap between COVID vaccine doses due to limited supply

The recommendation applies to all COVID-19 vaccines currently approved in Canada

A vial of Oxford-AstraZeneca COVID-19 vaccine is pictured at a family doctor office, Thursday, Feb. 25, 2021 in Paris. THE CANADIAN PRESS/AP -Christophe Ena
Trudeau ‘optimistic’ that timeline for rollout of COVID vaccines can be accelerated

Canada set to receive more than 6M COVID-19 vaccine dose than initially expected, by end of March

Most Read