Size of LNG Canada’s natural gas liquefaction faciity at Kitimat is revealed in this scale model of the greater Kitimat area. The plant location is the cleared area just above the ‘S’ curve section of the Kitimat River. (Photo courtesy LNG Canada)

LNG Canada cost to exceed stated $40 billion price tag

Gas pipeline alone pegged at $6.2 billion

The frequently quoted $40 billion (CDN) price tag for the construction of LNG Canada’s natural gas liquefaction plant in Kitimat is likely to be exceeded once construction is completed.

That’s because the price tag so far only includes two of the four massive “trains”, steel production units planned for the 250 hectare-plus plant location at Kitimat that will super-cool natural gas into liquid form for transfer to waiting tankers for the journey across the Pacific to Asian customers.

There’s no decision yet to add the third and fourth trains but LNG Canada officials describe their costs as “incremental” given the infrastructure work already underway for the first two trains.

Together those first two trains will have the capability of producing 14 million tonnes of LNG annually. By comparison, an LNG plant in Lousiana built by Cheniere Energy Partners LP, which was completed in 2016 and which has been adding capacity ever since, is scheduled to produce 22.5 million tonnes a year when a fifth train is finished next year.

To date the largest LNG Canada project cost component is the overall engineering, procurement and construction contract which has gone to two companies, American-based Fluor and JGC from Japan, working as joint venture partners (JFJV).

That contract value is placed at just under $18.5 billion, divided into just over $11 billion for Fluor and just under $7.5 billion for JGC.

“Approximately 60 per cent of the total budget for the overall project will be spent in British Columbia. The remainder will be spent in other parts of Canada, and overseas for construction of the modules,” said LNG Canada director of external relations Susannah Pierce.

The next big ticket item is TransCanada’s Coastal GasLink 670 kilometre-long pipeline which will carry natural gas from northeastern B.C. to Kitimat.

That pipeline’s construction cost is $6.2 billion, of which $620 million has been awarded to various First Nations-affiliated companies along the route.

By itself, Coastal GasLink is arguably the second largest private sector project in Canadian history, topping Rio Tinto’s Kitimat aluminum smelter rebuild which was pegged at $6 billion.

Other costs connected to LNG Canada itself include site preparation, dredging of two wharves and the rebuilding of an existing wharf where the LNG-carrying tankers will dock.

The existing wharf had been owned by Rio Tinto but a $567 million deal has now placed it under the control of LNG Canada.

The costs also include the diversion of creeks at the plant location, environmental mitigation and the years-long expenditures incurred steering the project through to obtaining environmental approvals.

Over and above the site construction and associated works, and the pipeline, are costs being borne by LNG Canada’s prime investors — Shell, Malaysian-state owned Petronas, PetroChina, Mitsubishi from Japan and Korean-owned KOGAS.

Their expenditures include collecting the northeastern natural gas and supplying the tankers for transporting the final super-cooled fuel overseas.

Those costs are contained within the overall $40 billion project total, with Pierce citing the information as “commercially sensitive.”

Also unknown, and a factor which could help push the project over and above that $40 billion figure, is the prospect of LNG Canada having to pay import tariffs on the fabricated industrial steel components making up the modules included in the trains.

Those tariffs were introduced by the federal government in response to lobbying by eastern steel manufacturers who argued that steel, from mostly Asian countries, was being dumped on the Canadian market below-cost, creating an uneven playing field for domestic producers.

Prior to LNG Canada being given the official go-ahead in early October, the company had been strenuously arguing for relief from the tariffs, saying the size of the modules was beyond the production capacity of domestic producers who had even suggested they could create a lower mainland B.C. base for their production.

The modules, at 50 metres high or the equivalent of a residential building 17 storeys tall, would be constructed overseas, transported by barge to Kitimat and then assembled on site.

Ahead of the announcement of the Final Investment Decision made on October 1, LNG Canada had hinted that the potential added cost, estimated at $1 billion by some analysts, could affect a final investment decision.

The matter is now before the Federal Court of Appeal and with the project now going ahead regardless, Pierce says the company is hopeful of a decision in its favour.

“LNG Canada remains confident in our position that large, complex LNG modules cannot be constructed in Canada, and therefore would not harm the domestic industry. As such, they should not be [tariff] subject goods,” she said.

“The total project cost assumes we have been successful in the argument we made to government in our application with respect to the application of anti-dumping and countervailing duties on large complex modules required by LNG Canada.”

The company also says there is plenty of steel required for other portions of the project that could come from domestic producers.

As an example, it says civil and earthworks and associated needs require 13,000 metric tonnes of rebar alone.

Just Posted

Pilot project thins out overgrown forest location

Immediate and long term logging and environmental benefits eyed

Gitga’at and LNG Canada announce new Marine Emergency Response and Research Facility in Hartley Bay

LNG Canada providing financial support as committed in 2014 Impact Mitigation and Benefit Agreement

Chevron’s move to exit Kitimat LNG project a dash of ‘cold water’ for gas industry

Canada Energy Regulator approved a 40-year licence to export natural gas for Kitimat LNG

Snowfall warning continues for parts of B.C.’s Interior

First significant snowfall of the season prompts Environment Canada warning

VIDEO: Success of wildlife corridors in Banff National Park has advocates wanting more

Demand for more highway protection escalated after seven elk were killed by a semi-trailer near Canmore

Pacioretty scores 2, Golden Knights top Canucks 6-3

Vegas goalie Fleury gets win No. 452

B.C. VIEWS: Hunger does not end with the season

Despite innovations in food distribution, the need is still there in B.C. communities

Fans sing Canadian anthem after sound system breaks at BMW IBSF World Cup

The Canadians in attendance made sure their team and flag were honoured on the podium

VIDEO: Fire destroys Big White Ski Resort chalet

Social media eulogies peg the property, nicknamed “The Pharamacy,” as both loved and hated

Prince George RCMP use bait packages to catch porch pirates over the holidays

First-in-Canada program with Amazon looks to combat parcel theft

Nanaimo mechanical engineer creates thief tracking program

Nanaimo Thief Tracking lets users plot and share information about thefts online

Mayor wants B.C. to institutionalize severely mental ill people who are homeless

Those suffering from mental health conditions, such as schizophrenia, need specialized care, mayor says

Most Read