Size of LNG Canada’s natural gas liquefaction faciity at Kitimat is revealed in this scale model of the greater Kitimat area. The plant location is the cleared area just above the ‘S’ curve section of the Kitimat River. (Photo courtesy LNG Canada)

LNG Canada cost to exceed stated $40 billion price tag

Gas pipeline alone pegged at $6.2 billion

The frequently quoted $40 billion (CDN) price tag for the construction of LNG Canada’s natural gas liquefaction plant in Kitimat is likely to be exceeded once construction is completed.

That’s because the price tag so far only includes two of the four massive “trains”, steel production units planned for the 250 hectare-plus plant location at Kitimat that will super-cool natural gas into liquid form for transfer to waiting tankers for the journey across the Pacific to Asian customers.

There’s no decision yet to add the third and fourth trains but LNG Canada officials describe their costs as “incremental” given the infrastructure work already underway for the first two trains.

Together those first two trains will have the capability of producing 14 million tonnes of LNG annually. By comparison, an LNG plant in Lousiana built by Cheniere Energy Partners LP, which was completed in 2016 and which has been adding capacity ever since, is scheduled to produce 22.5 million tonnes a year when a fifth train is finished next year.

To date the largest LNG Canada project cost component is the overall engineering, procurement and construction contract which has gone to two companies, American-based Fluor and JGC from Japan, working as joint venture partners (JFJV).

That contract value is placed at just under $18.5 billion, divided into just over $11 billion for Fluor and just under $7.5 billion for JGC.

“Approximately 60 per cent of the total budget for the overall project will be spent in British Columbia. The remainder will be spent in other parts of Canada, and overseas for construction of the modules,” said LNG Canada director of external relations Susannah Pierce.

The next big ticket item is TransCanada’s Coastal GasLink 670 kilometre-long pipeline which will carry natural gas from northeastern B.C. to Kitimat.

That pipeline’s construction cost is $6.2 billion, of which $620 million has been awarded to various First Nations-affiliated companies along the route.

By itself, Coastal GasLink is arguably the second largest private sector project in Canadian history, topping Rio Tinto’s Kitimat aluminum smelter rebuild which was pegged at $6 billion.

Other costs connected to LNG Canada itself include site preparation, dredging of two wharves and the rebuilding of an existing wharf where the LNG-carrying tankers will dock.

The existing wharf had been owned by Rio Tinto but a $567 million deal has now placed it under the control of LNG Canada.

The costs also include the diversion of creeks at the plant location, environmental mitigation and the years-long expenditures incurred steering the project through to obtaining environmental approvals.

Over and above the site construction and associated works, and the pipeline, are costs being borne by LNG Canada’s prime investors — Shell, Malaysian-state owned Petronas, PetroChina, Mitsubishi from Japan and Korean-owned KOGAS.

Their expenditures include collecting the northeastern natural gas and supplying the tankers for transporting the final super-cooled fuel overseas.

Those costs are contained within the overall $40 billion project total, with Pierce citing the information as “commercially sensitive.”

Also unknown, and a factor which could help push the project over and above that $40 billion figure, is the prospect of LNG Canada having to pay import tariffs on the fabricated industrial steel components making up the modules included in the trains.

Those tariffs were introduced by the federal government in response to lobbying by eastern steel manufacturers who argued that steel, from mostly Asian countries, was being dumped on the Canadian market below-cost, creating an uneven playing field for domestic producers.

Prior to LNG Canada being given the official go-ahead in early October, the company had been strenuously arguing for relief from the tariffs, saying the size of the modules was beyond the production capacity of domestic producers who had even suggested they could create a lower mainland B.C. base for their production.

The modules, at 50 metres high or the equivalent of a residential building 17 storeys tall, would be constructed overseas, transported by barge to Kitimat and then assembled on site.

Ahead of the announcement of the Final Investment Decision made on October 1, LNG Canada had hinted that the potential added cost, estimated at $1 billion by some analysts, could affect a final investment decision.

The matter is now before the Federal Court of Appeal and with the project now going ahead regardless, Pierce says the company is hopeful of a decision in its favour.

“LNG Canada remains confident in our position that large, complex LNG modules cannot be constructed in Canada, and therefore would not harm the domestic industry. As such, they should not be [tariff] subject goods,” she said.

“The total project cost assumes we have been successful in the argument we made to government in our application with respect to the application of anti-dumping and countervailing duties on large complex modules required by LNG Canada.”

The company also says there is plenty of steel required for other portions of the project that could come from domestic producers.

As an example, it says civil and earthworks and associated needs require 13,000 metric tonnes of rebar alone.

Just Posted

Grim situation in coming year for northwest, B.C. fisheries

Annual post-season review in Prince Rupert informs DFO on how to manage 2019 fishing season

Two projects to tackle Haisla housing shortage

B.C. government plans to build more than 280 homes across nine communities in the north

Museum and Haisla Nation Council sign MOU

MOU further strengthens the existing relationship

VIDEO: Dog behaviourist holds classes to raise funds for NARA

Holidays are a busy time for rescue agencies

VIDEO: Close encounter with a whale near Canada-U.S border

Ron Gillies had his camera ready when a whale appeared Dec. 7

2 facing animal cruelty charges after emaciated dog found in B.C.

Amy Hui-Yu Lin and Glenn Mislang have been charged with causing an animal to continue to be in distress

Out of the doghouse: B.C. city lifts ban on pup who barked too much at dog park

Cameron the Shetland sheepdog is allowed back into Uplands off-leash dog park under some conditions.

No flood of extremist returnees to Canada expected, federal report says

The report says some 190 people with connections to Canada are suspected of terrorist activity abroad

Canada-China relations turn icy over arrest of Chinese exec

The Huawei case has threatened to complicate U.S.-China efforts to resolve a bitter trade dispute.

Prosecutor signs off on former B.C. Liberal government’s quick-wins probe

David Butcher said in a statement released Monday that the RCMP recommended charges under the Elections Act

Canadian physicist who won Nobel Prize touts science for the sake of science

Donna Strickland, 59, said securing the field’s highest honour has given her a significant new platform

Too many die in heavy truck crashes, B.C. auditor says

Province has no mandatory driver training for commercial vehicles

B.C. city considers scrapping funds for Christmas decorations

Victoria city coun. Ben Isitt doesn’t think the government should pay for any religious symbols

Most Read