Enridge responds to slide concerns

Enbridge is doing extensive geo-technical work to avoid the risk of landslides along the proposed route of the Northern Gateway pipelines...

Andrew Hudson

Enbridge is doing extensive geo-technical work to avoid the risk of landslides along the proposed route of the Northern Gateway pipelines, says director of engineering Raymond Doering.

“We understand, totally, the features in the area that have resulted in slides that might have affected other pipelines or highways or railways,” he said.

“What we’ve done is work to identify a route that avoids those hazards.”

Doering said the proposed route runs south of existing pipelines, such as the Pacific Natural Gas pipeline that crosses the Telkwa Pass.

Other new pipeline proposals, like the Pacific Trails Pipeline, are following that lead.

Over the last 30 years, landslides cut the more northern PNG pipeline three times.

But geotechnical knowledge has come a long way since then, Doering said.

For example, he said, surveyors now realize why it’s important to know that some 10,000 years ago, the Kitimat Valley was the bottom of the ocean. That land rebounded as Ice Age glaciers melted away, leaving pockets of glacial marine clay that is unstable.

“That’s a very well understood condition now,” Doering said. “But it wasn’t well understood when the original PNG pipeline was routed down to Kitimat over 40 years ago.”

Enbridge is doing ongoing fieldwork – digging bore holes, doing remote-sensing flyovers and aerial photography – to assess such risks, he said. It began its geo-technical surveys in 2005 and last year the company submitted a long report detailing its geo-technical surveys for the Joint Review Panel that is assessing the project.

“We don’t just look on the corridor,” Doering explained. “We look as far to either side of the corridor as necessary, and sometimes it’s many kilometres.”

Wherever possible, he said the proposed route avoids geohazards. And where hazards are unavoidable, his team will engineer ways to mitigate risk.

For example, Enbridge plans to dig two tunnels, one 6.5 km and one 6.6 km long, to route its twin pipelines under the Coast Mountains.

“It’s a huge investment,” he said. “But it’s a huge investment in the safety of the workers and for the long-term operation in the pipeline.”

Doering was responding to concerns raised in a recent report by James Schwab, a retired geomorphologist, that was published by the Bulkley Valley Research Centre.

The Schwab report concluded that landslides will eventually cut any pipeline routed through west central BC (Northern Sentinel, October 26).

But in his study, Doering said that Schwab did not make specific reference to the Enbridge proposal or any of the geo-technical information it has filed with the panel.

“We are already generating a response, section by section, which will be on the public record,” he said. “We’re prepared to describe the lengths we’ve gone to mitigate and avoid those hazards.”

Doering said he expects the Schwab report will be included among the 215 other intervenors who have submitted information requests to the Joint Review Panel. “They are important questions, there’s no doubt,” he said. “People want to make sure you are doing the work. And we are being as thorough as we can be.”

A full record of the Enbridge proposal is available on the Joint Review Panel website at gatewaypanel.review-examen.gc.ca.

 

Just Posted

Province announces $100-million grant funding for Northwest communities

The Northern Capital and Planning Grant will go to four regional districts and 22 municipalities

LNG Canada sponsors fast-tracked driver’s license training in Terrace, Kitimat

The $80,000 contribution is part of the company’s commitment to hire locally

Prince Rupert Gas Transmission project searches for partners

TransCanada is renewing permits for its natural gas pipeline project to North Coast.

Coastal GasLink stops work to investigate archaeological find

OGC archaeologists are en route to the Houston-area site where Unist’ot’en report finding stone tools

All Native Basketball Tournament Day 5: Recap

Highlights and results from day 5 at the All Native Tournament

B.C. students win Great Waters Challenge video contest

Video, mural and song about saving the salmon claims the top prize

B.C. athlete takes home gold in freestyle aerials at Canada Games

Brayden Kuroda won the event with a combined score of 121.65.

Cabinet likely to extend deadline to reconsider Trans Mountain pipeline

New round of consultations with Indigenous communities is coming

B.C. government provides $75,000 towards salmon study

Study looks at abundance and health of Pacific salmon in Gulf of Alaska

Murdered and missing honoured at Stolen Sisters Memorial March in B.C.

‘We come together to make change within the systems in our society’

UBC researchers develop inexpensive tool to test drinking water

The tricoder can test for biological contamination in real-time

Disgraced ex-Congressman Anthony Weiner released from prison

He was convicted of having illicit online contact with a 15-year-old North Carolina girl in 2017

B.C. communities push back against climate change damages campaign

Activists copying California case that was tossed out of court

Most Read