B.C. Supreme Court hears petition for judicial review of Coastal GasLink certificate

B.C.’s Environmental Assessment Office granted Coastal GasLink an extension last October
22875915_web1_200219-SIN-CGL-back-to-work-pipes_1
Coastal GasLink pipe segments stored at the port in Stewart. Company expects sections to start arriving at Houston site later this month. (File photo)

Lawyers for the Office of the Wet’suwet’en are in British Columbia Supreme Court today seeking an order quashing the extension of the environmental assessment certificate for a pipeline that was at the centre of countrywide protests in February.

The executive director of B.C.’s Environmental Assessment Office granted Coastal GasLink an extension last October, nearly five years after a certificate was first issued for the 670-kilomtre pipeline meant to carry natural gas from the Dawson Creek area to Kitimat, where it would be converted to liquid for export.

A petition filed in February on behalf of the Office of the Wet’suwet’en, a non-profit society governed by several hereditary chiefs, says environmental assessment certificates set a deadline of five years, by which time a project must be “substantially” underway.

The document says the assessment office confirmed that the factors informing the director’s decision to grant Coastal GasLink a one-time extension included the company’s compliance record, as well as “potential significant adverse effects that would require revisions” to the certificate and its conditions.

But lawyers for the Office of the Wet’suwet’en say the environmental assessment office failed to determine whether the report from the National Inquiry into Missing and Murdered Indigenous Women and Girls released last summer raised such changes or consider an analysis of gender-based harms associated with the pipeline project.

They’re also arguing that the records used to make the director’s decision failed to address more than 50 instances of non-compliance with existing conditions in a 10-month period starting in January 2019.

While they’re arguing the decision to grant the extension was unreasonable and unjustifiable, the response to the petition filed on behalf of the environmental assessment office says there is no merit for the judicial review.

It argues the petition conflates a summary report by the assessment office that recommended the approval with the decision of the executive director, saying the report is an important component of the record of the decision but it’s not correct to describe it as the reasoning.

The hereditary chiefs have opposed Coastal GasLink’s pipeline project, while five elected Wet’suwet’en band councils signed agreements with the company approving construction.

The Canadian Press