Undersea cable pitched for clean energy

A company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids

Wind farm development in northeastern B.C. Proponents of a new power line between Vancouver Island and Washington say it would make wind power a more stable source.

VICTORIA – With BC Hydro struggling to control electricity rate increases and cutting back on private power acquisition, a company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids.

Sea Breeze Power Corp. wants to build a 50 km transmission cable under the Strait of Juan de Fuca to connect substations near Port Angeles and Victoria. To finance the project, it’s looking for a 10-year deal to assemble surplus U.S. power and sell it to BC Hydro at a flat rate of $69 per megawatt hour.

Sea Breeze CEO Paul Manson said the power purchase would finance the construction of the cable and deliver a steady source of electricity to B.C. at lower cost than new sources built in the province. It would also improve power quality and reliability for Vancouver Island residents, he said.

First proposed in 2006, the project has received environmental permits from both sides of the border. It was rejected by the B.C. Utilities Commission, which approved upgrading the existing power line from the B.C. mainland to Vancouver Island instead.

Sea Breeze developed a wind project at Cape Scott on northern Vancouver Island, and has plans and permits for other wind sites on the B.C. coast and the Peace River region. Manson said the Juan de Fuca cable would stabilize wind power supply on the B.C. coast, where wind speeds peak in winter, with inland Washington sites where it’s windiest in summer.

Manson said U.S. policy led to major wind development that leaves the the Pacific Northwest with an excess of power in spring, meaning the Washington power utility has paid BC Hydro to take its excess when hydro dams are full.

The cable would also give B.C. more capacity to buy cheap overnight coal and nuclear power from the U.S., which BC Hydro already does with its main connecting line along Interstate 5, he said.

Energy Minister Bill Bennett said the Juan de Fuca cable is one of many proposals that came forward as BC Hydro developed its integrated resource plan. That plan estimates that with conservation and efficiency improvements in B.C., the province will need more electricity supplies within eight years.

The company has not yet demonstrated that it can assemble the firm electricity it proposes to sell, and the project has “a pretty steep slope to climb,” Bennett said.

 

Just Posted

PHOTO GALLERY: Malicious Monster Truck Tour

The Malicious Monster Truck Tour sold out to crowds of 2,500 people… Continue reading

North Coast fishing grounds key to orca recovery: DFO

Plan marks waters from Langara to Rose Spit as critical habitat for northern resident killer whales

Chris Green, mother of scouts, passes away

Green, who was born near Kitimat, spent more than 60 years volunteering with Scouts Canada

Intertidal Music Festival back for round two

More than 20 performances throughout the day at the North Pacific Cannery on July 21

Alberta man missing on Kitimat River found dead

Body found on July 11 after going missing on July 7

BC Games’ Athletes Corner: What’s your favourite pump up song?

Check out what’s playing in the earbuds of BC Summer Games athletes before they compete

Crosswalk vandalism leaves black mark for Cowichan as B.C. Games begin

Rainbow crosswalk defaced just days after being painted

Photo gallery: BC Games Day 1

A brief look at action from the 2018 BC Summer Games in the Cowichan Valley

Anti-pipeline campers digging in as eviction deadline expires

The City of Burnaby had ordered the Kinder Morgan pipeline protesters out for violating bylaws

Trump was taped talking of paying Playboy model: AP source

Source says former personal lawyer Michael Cohen secretly recorded discussion prior to 2016 election

BC toddler with ‘allergy’ to sun waiting for bone marrow transplant

Charlie Lock, 2, needs treatment for damage caused by rare disorder EPP

VIDEO: How to throw a frisbee

Ultimate frisbee player Amy Mackay shows off the proper technique

Site C dam project plagued by problems: expert

E. Harvey Elwin expresses concern about internal BC Hydro and government documents

Seal attacks kayakers off northern Vancouver Island

‘It has to be one chance in a million of this happening.’

Most Read